Sandy City, UT Logo
File #: SPR-03-19-5631    Version: 1 Name:
Type: Planning Item Status: Agenda Ready
File created: 5/6/2019 In control: Planning Commission
On agenda: 5/16/2019 Final action:
Title: Centennial Towers (Revised) – Phase 1 Preliminary Site Plan Review 215 W. Sego Lily Drive [Community #9 – South Towne]
Attachments: 1. Staff Report.pdf, 2. ARC Minutes 4.24.19.pdf, 3. requested excpetions.pdf, 4. requested excpetions map.pdf, 5. 2019-05-06 Centennial Towers - Civil Set.pdf, 6. Landscape Set.pdf, 7. Building Materials_CENTENNIAL TOWERS 4-24-19.pdf, 8. Parking Structure looking Northwest.pdf, 9. Parking structure West side.pdf, 10. Town homes 10080 Street looking Northeast.pdf, 11. Town homes 10080 Street.pdf, 12. Condominium tower elevations.pdf, 13. Condominium tower rendering 2.pdf, 14. Condominium tower rendering base.pdf, 15. Condominium tower rendering.pdf, 16. Condominium towerelevations b.pdf, 17. Hotel elevations b.pdf, 18. Hotel elevations.pdf, 19. Hotel looking Southwest.pdf, 20. office building elevations b.pdf, 21. office building elevations .pdf, 22. office building rendering.pdf
Related files: SPR-06-18-5420, SPR12282021-006237
Agenda Item Title:
Title
Centennial Towers (Revised) – Phase 1 Preliminary Site Plan Review
215 W. Sego Lily Drive
[Community #9 – South Towne]

Body
Presenter:
Mike Wilcox

Body
Description/Background:
Mr. Russell Platt of Russell Platt Architecture, representing the property owners Centennial Towers, LLC and Truong Properties, has submitted an application for a revised Phase 1 preliminary site plan of the Centennial Towers Project. The proposal is part of the 4.27 acre master planned development that would incorporate an entire block. It is also part of the South Village Area in the Cairns Master Plan. The master plan is mostly unchanged as to building placement from the previous approval in September of 2018. There are a few difference in uses, design, and phasing with the current version of the plan. The revised site plan indicates that the project is to be completed in two (2) phases rather than four (4) phases as was previously proposed. This first phase of this project now includes three (3) new buildings (condo, office and hotel towers), a remodel of the existing office/retail building, a new service alley, an extension of 10080 South (public road), an expanded parking structure, and eight (8) new townhome units. A future second phase now includes a residential tower on the southeast corner of the block, and a new office/retail building along Monroe Street in front of the parking garage.

Recommended Action and/or Suggested Motion:
Recommendation
Staff recommends that the Planning Commission find that the preliminary site plan review is complete for Phase 1 of the Centennial Towers development located at approximately 215 W Sego Lily Dr, based upon the following conditions:

Conditions:

1. That street improvements be carried out according to Plan and Profiles approved by the Sandy City Engineer and specifically:

a. That Centennial Parkway be further improved and dedicated to includ...

Click here for full text