Agenda Item Title:
Title
Public Utilities Department recommending the City Council approve Dry Creek Flood Control Project interlocal funding agreement with Salt Lake County
Body
Presenter:
Tom Ward
Description/Background:
In January, the Sandy City Dry Creek Concept Plan was completed, which summarizes the overall plan for the Dry Creek Corridor from Jordan River to Bell Canyon Reservoir. As part of the presentation on February 27, Tom Ward will discuss the purpose for and elements of the Dry Creek Flood Control and Parkway Project. Phase 1 (I-15 to Monroe Street) of the Dry Creek improvements was completed in fall of 2016. Construction on Phase 2 (Monroe Street to Centennial Parkway - Southbound) will begin in April of this year. Salt Lake County (County) is contributing $200,000 to the Dry Creek Improvements project for 2018 and has verbally committed at least $200,000 per year until the project is complete. The interlocal agreement with Salt Lake County and Sandy City defines the terms for the $200,000 contribution from the County.