Skip to main content
Sandy City, UT Logo
File #: 25-234    Version: 1 Name:
Type: Informational Report Status: Agenda Ready
File created: 7/22/2025 In control: City Council
On agenda: 7/29/2025 Final action:
Title: City Administration requesting Council approval of the updated cost estimates for the rebuild of the Alta Canyon Sports Center
Attachments: 1. Alta Canyon Funding Options
Related files: 24-448, 25-227

Agenda Item Title:

Title

City Administration requesting Council approval of the updated cost estimates for the rebuild of the Alta Canyon Sports Center

 

Body

Presenter:

Dan Medina, Parks & Recreation Director

Martin Jensen, Deputy Chief Administrative Officer

 

 

Body

Description/Background:

On December 17, 2024 the City Council, by motion, approved the design concept and cost estimates for the design and rebuild of the Alta Canyon Sports Center.  Following the design process, the City Administration provided the Council with an update on the design process and cost estimates on July 15, 2025.  Due to the many factors presented to the Council on July 15th, the estimated cost to rebuild the center has increased to $23.5 million.  As the estimated cost has exceeded what the Council originally approved, the Administration is requesting approval of the updated cost estimate.

 

 

Recommended Action and/or Suggested Motion:

Recommendation

Motion directing staff to proceed with the $23.5 million design option for the Alta Canyon Sports Center as presented to the Council on July 15, 2025.