File #: SPR-08-18-5468    Version: 1 Name:
Type: Planning Item Status: Passed
File created: 9/10/2018 In control: Planning Commission
On agenda: 9/20/2018 Final action: 9/20/2018
Title: Union Peaks Office Building 7585 South Union Park Ave. [High Pointe, Community #6]
Attachments: 1. Staff Report.pdf, 2. Exhibits.pdf

Agenda Item Title: 

Title

Union Peaks Office Building

7585 South Union Park Ave.

[High Pointe, Community #6]

 

Body

Presenter: 

Doug Wheelwright

 

Body

Description/Background:

The applicant, Mr. Connor Johnson, representing Thrive Development, is requesting that the Planning Commission consider and approve Site Plan Review for the proposed Union Peaks Office Building development. The Planning Commission is the land use approval body for site plan review in this zoning district, as designated in the Sandy City Development Code.

 

 

Recommended Action and/or Suggested Motion:

Recommendation

Staff recommends that the Planning Commission approve the proposed Union Peaks Office Building project, located at 7585 South Union Park Avenue, as proposed, including approving the proposed building height and modifying the Architectural Design Standards to not require the 18 inch roof eve overhang, based on the staff report, and the two findings listed below and subject to the following eight conditions:

 

FINDINGS:

 

A.                     That the various City Departments and Divisions, including the City Engineer and the Transportation Engineer, have preliminarily approved the proposed site plan.

 

B.                     That the proposed building design, materials and colors meet the Sandy City Architectural Design Requirements, as modified by the Planning Commission,

 

 

CONDITIONS:

 

1.                     That the developer proceed through the final site plan review process with staff prior to the start of any construction (including payment of development fees and posting of an appropriate bond to guarantee completion of all required improvements on and off the site), according to the Site Plan Review Procedures Handout.  The final site plan shall comply with all Development Code requirements and those modifications required and approved by the Planning Commission.

 

2.                     That the development comply with all Building & Safety, Fire and Life Safety Codes applicable to this type of use.

 

3.                     All utility boxes shall be screened from view to the extent possible (i.e. transformers, switch gear, telephone, cable TV, etc.) and shall be shown on the site plan and shall be placed underground or moved behind the front setback (minimum of 30 feet from the front property line).  Each box shall be shown in its exact location and shall be noted with its exact height, width and length and approved by staff as part of the final site plan.

 

4.                     That the architectural design, colors and materials, proposed for this development and as approved by the Planning Commission as complying with the Sandy City Architectural Design Standards, be finalized with staff prior to the issuance of a building permit.

 

5.                     That the developer be responsible for the placement of a temporary 6 foot high chain link fence around the perimeter of the project during the construction phase of the project for security.  Said fence shall also be required to include fabric to prohibit blowing dust problems, if it becomes necessary or if it is required by the Community Development Department during Site Plan Review.

 

6.                     That the applicant comply with the Sandy City Noise Ordinance, including working hours during construction.

 

7.                     That the applicant comply with all department requirements as noted in all Preliminary Review letters prior to submittal for final site plan review.

 

8.                     That the future wall sign for this office building must comply with the Sandy City Sign Ordinance relative to wall signs for multi-tenant buildings.