Agenda Item Title:
Title
The Meadows at Cys Road (Site Plan Review)
8777 S. 700 E.
[Community #7, Quarry Bend]
Body
Presenter:
Thomas Irvin, Senior Planner
Body
Description/Background:
The applicant and property owner, Brad Reynolds of Cy Meadow, LLC, is requesting a preliminary Subdivision and Site Plan review for the property located at approximately 8777 S. 700 E. The proposal includes developing the property into 33 residential units consisting of seven single family homes and 26 town homes. The property will also be subdivided into a residential condominium allowing for the private ownership of units. Based upon the applicant’s submittal, three special exceptions will also be required for the current design which include the following: the creation of private streets instead of public streets, the creation of lots which do not front onto a public street, and the creation of streets with less than the standard street right-of-way width.
The property is zoned Planned Unit Development (PUD) which requires that the Planning Commission review and approve the proposed building materials, building design, exterior fencing, landscape (open space), and amenities for the project. The Planning Commission may also require specific setbacks, buffers, building heights, and site arrangements where it is determined to be appropriate. The Planning Commission reviews developments within the PUD zone to ensure the site plan follows the purpose and design objectives outlined in the ordinance. Additionally, the proposed Subdivision and Special Exceptions require Planning Commission review.
Please see the attached staff report and exhibits for full details of the application.
Recommended Action and/or Suggested Motion:
Recommendation
Staff recommends that the Planning Commission determine that the preliminary site plan review for The Meadows at Cys Road located at 8777 S. 700 E is substantially complete based on the following findings and subject to the following conditions:
Findings:
1. That the proposed configuration is an efficient use of the land.
2. That the proposed development substantially complies with the requirements of the Planned Unit Development zone.
3. That the various City Departments and Divisions have preliminarily approved the proposed subdivision plat.
Conditions:
1. That the applicant complies with each department’s comments and redlines throughout the final review process and that all issues be resolved before the development can be approved.
2. That all city provisions, codes, and ordinances are adhered to during the review, construction, and operations process of this project.
3. That the Planning Commission determine an appropriate amenity package for the application.